November 1st New Pipeline Projects

Updated: Nov 12, 2019


Complex Chemical

Tallulah, LA


1000' 8"


New line to be built at the Madison Parish Port on the Mississippi River near Tallulah, LA.


Early Stages

No Timetable


Flint Hills Resources

Wichita, KS


5 mi. 4"


This pipeline will transport liquified petroleum from its refinery in Rosemount to its terminal in Inver Grove Heights, MN.


Construction early 2020


Bridger Pipeline, LLC

Casper, WY


191 mi. 20"


The "Equality" pipeline will run from Hulett to near Guernsey, WY.


Construction late 2019 or early 2020


Bridger Pipeline, LLC

Casper, WY


137 mi. 16"


The "South Bend" pipeline will run from Johnson Corner, ND to near Baker, MT.


Construction mid 2020